Marshall Space Flight Center (NASA)

ERH, TCH and SEE ISTR at a Complex, High-Security Site

Remediation Solution

Remediation Approach

Technology

Contaminant Mass
Recovered

63,016 lbs

Media Treated

Soil & Groundwater – Silty clay and gravel layers of overlying limestone bedrock

Industry

Contaminant Type

Contaminant of Concern

PCE, TCE

Location

Alabama,
USA

Challenge

Source Area 13 (SA-13) at NASA’s Marshall Space Flight Center in Huntsville, Alabama, sits between Buildings 4703 and 4705, where missile assembly and paint shop operations ran from the 1950s through the 1970s. Crews used trichloroethylene (TCE) and related solvents to degrease equipment, and spills and leaking drums released TCE, PCE, and other chlorinated VOCs into soil and groundwater.

Groundwater concentrations reached 640,000 µg/L, roughly half of TCE’s solubility limit in water. A common screening rule treats anything above 1% of solubility as a sign of DNAPL, so this level points strongly to residual DNAPL acting as a long-term source. Soil concentrations reached 240 mg/kg.

Site conditions ruled out a single-technology approach:

  • Mixed lithology. Silty clay, gravel layers, and limestone bedrock each take up heat differently. Tight clay resists fluid flow, gravel moves groundwater that can carry heat away, and bedrock is hard to drill and heat evenly.
  • Unknown subsurface obstructions. Unmarked utilities and subsurface voids surfaced during installation, forcing design changes in the field.
  • Limited site power. The available power could not run all three heating systems across the full 40,000 ft² at once.
  • Extraction control. Pulling vapor and liquid at the same time from a heated, mixed-permeability zone required holding pneumatic and hydraulic control for the full program.
  • Active, high-security federal facility. Crews held temporary or year-long NASA badges, with access to restricted areas only as the work required. Deliveries were limited to weekday daytime hours through a designated gate, and work hours and consecutive workdays were capped. Photography inside buildings and use of NASA networks were prohibited. NASA operations continued alongside the remediation throughout.

The remedial objective was demanding: hold most of the treatment zone above 194°F (90°C) for at least 90 days, then keep operating until VOC recovery went asymptotic.

Site Conditions

  • Deep Treatment
  • Large Volume
  • Variable Geology
  • LNAPL
  • Mixed Contaminants
  • Unexpected Contaminants
  • Underground utilities
  • DNAPL
  • Energy/Utility
  • Fractured Bedrock
  • Active Facility
  • Hydrogeologic
  • Infrastructure & Access
  • Large Plume

Approach

Under contract to Jacobs Engineering, VIYA designed, built, and operated the first in situ thermal remediation (ISTR) system to combine all three heating methods on one project. Those methods are IT-DSP™ (Inductive-Thermal Dynamic Stripping Process), ET-DSP™ (Electro-Thermal Dynamic Stripping Process), and steam-enhanced extraction (SEE). The design goal was to hold the subsurface above 194°F (90°C) across most of a 40,000 ft² treatment area for at least 90 days, driving chlorinated VOCs to asymptotic recovery.

  • Matching heat to geology. Silty clay, gravel, and limestone bedrock each take up heat differently, so no single method could heat the whole zone evenly. VIYA paired IT-DSP™ heaters for tight clay and bedrock, ET-DSP™ electrodes for variable geology, and steam injection for permeable gravel.
  • Modeling before drilling. VIYA used 3D thermal models to plan heater and well locations, helping prevent hot and cold spots and achieve even heating above 194°F (90°C).
  • Drilling into bedrock. Sonic drilling advanced heater and sensor wells into the limestone bedrock, and well locations were adjusted in the field around unmarked utilities and voids.
  • Phasing to fit available power. The program was split into two phases to stay within the site’s power supply: 2,000 kVA and 2,500 kVA transformers at SA-13, and a 750 kVA transformer at SA-12.
  • Field-scale deployment. VIYA installed 148 IT-DSP™ heaters, 16 ET-DSP™ electrodes, 10 steam injection wells, and a multiphase extraction network across 40,000 ft².
  • Extraction and treatment. Recovered vapor and liquid passed through a VIYA-built treatment plant using air stripping and granular activated carbon. Fiber-optic sensors tracked subsurface temperatures in real time so heating and extraction could be tuned throughout operations.
  • Working inside an active NASA facility. The schedule was adjusted when needed to accommodate ongoing NASA operations.

Results

The combined system met every remedial objective. The treatment zone held above 194°F (90°C) for the required 90 days, peaked at 220°F (104°C), and kept extracting until VOC recovery went asymptotic.

  • 63,016 lbs of chlorinated VOCs removed: 22 times the original design estimate, showing that significantly more contamination was present than expected.
  • Greater than 99% system uptime over 273 days: January to October 2024, despite power outages and Alabama summer heat. A backup generator kept the treatment plant running whenever site power dropped.
  • 16,146 MWh delivered through 148 IT-DSP™ heaters, 16 ET-DSP™ electrodes, and 10 steam injection wells.
  • Safe work through summer heat: crews followed a heat-stress program of scheduled breaks in vehicles and air-conditioned space, hydration, electrolyte replacement, and body temperature monitoring.
  • First project to combine IT-DSP™, ET-DSP™, and SEE in one system, demonstrating how the three technologies can work together to treat different ground conditions.

Related Case Studies

Learn What’s VIYABLE

Let's Begin Your Path Forward.